0
0

Delete article

Deleted articles cannot be recovered.

Draft of this article would be also deleted.

Are you sure you want to delete this article?

[Cost Management] EVM(Earned Value Management)

Last updated at Posted at 2024-10-05

一覧

EVM指標
PV
Planned Value
計画時の出来高
EV
Earned Value
完了した作業の出来高
AC
Actual COat
実際に費やしたコスト
BAC
Budget At Completion
完成時総予算
現時点での状況評価
CV
Coat Variane
負ならコスト超過
EV-AC
SV
Schedule Variance
負なら計画遅れ
EV-PV
CPI
Cost Performance Index
CPI<1ならコスト超過
EV/AC
SPI
Schedule Performance Index
SPI<1なら計画遅れ
EV/PV
将来の予測
ETC
残作業コスト予測
(BAC-EV)/CPI
EAC
完成時総コスト予測
AC+ETC
VAC
完成時コスト差異
BAC-EAC

参考リンク

0
0
0

Register as a new user and use Qiita more conveniently

  1. You get articles that match your needs
  2. You can efficiently read back useful information
  3. You can use dark theme
What you can do with signing up
0
0

Delete article

Deleted articles cannot be recovered.

Draft of this article would be also deleted.

Are you sure you want to delete this article?