C_TS422_2023 SAP Certified Application Associate SAP S/4HANA Production Planning and Manufacturing対策(8/100)

Posted at

【8日目】
トピック 2:SAPS/4HANA生産計画の概要(2/5)

≪問題8≫
生産の作業期間を決定するデータはどこで設定しますか。
(2つ選択)
□部品表/配合表(BOM)
□作業手順
□作業区
□品目マスタ

≪解答≫
□部品表/配合表(BOM)
■作業手順
■作業区
□品目マスタ

≪解説≫
生産における作業期間は、作業手順(Routing)と作業区(WorkCenter)に設定されます。これらのデータにより、各工程に必要な時間が定義され、生産スケジュールが最適化されます。